Work area by Alignment should not give 0 as start location station

Work Area by Alignment always starts at zero The tool always gives the start location station as 0, irrespective of the actual alignment property. Schedule/Work Areas are based on station points, so we have to manually do tons of calculations to s...
Arpit Prakash about 1 month ago in SYNCHRO Modeler / Work Area 0 Planned

Update work area and elements - HIGH PRIORITY

Cannot update Work Areas - HIGH PRIORITYThere's an option to click edit, but that doesn't let us remove selected/unwanted elements from the work area. Also, if there are changes to the polygon, there's no easy way to rerun the tool and get updated...
Arpit Prakash about 1 month ago in SYNCHRO Modeler / Work Area 2 Needs review

Add options to query quantities by Work Areas

Probably will need some details here.
Sarah Ruckhaus about 1 month ago in SYNCHRO Modeler / Slice / Work Area 2 Future consideration

Select elements from multiple selected work areas - High Priority

Cannot select multiple Work Areas - HIGH PRIORITY We typically create multiple small work areas per phases by selecting polygons in the iModel. E.g. Phase 1-Step 1.1, Phase 2- Step1.2, etc. This makes it easier to adapt to work area polygon change...
Arpit Prakash about 1 month ago in SYNCHRO Modeler / Work Area 2 Planned