Progress Measurement

Showing 13

Return Actual Cost to Work Inspector/Progress webpage

I note the New/Enhanced Feature for SYNCHRO Perform removed "Actual Cost" from the Progress page of the Work Inspector in 9-Jun-2024 update. This page reports "Revised Earned Cost" which is linked to the actual progress. This information is most u...
Ernest Downes 16 days ago in SYNCHRO Perform / Progress Measurement 0

Add current progress % next to progress bar for each activity in "All Activities" page

This is an idea from our programming team, which they find it very useful if can directly know the progress of each activity, with the aid of filtering function and WBS, instead of going to another page like "Quantity Progress", which doesn't have...
Tat Man Leung 13 days ago in SYNCHRO Perform / Program/Schedule Collaboration 0

Show earned quantity in the tagged item (ROC) view, in the cell for "actual quantity", actual is earned when doing ROCs

When doing rule of credit milestones, we need to know the current earned quantity based the approved milestone percentages. We shouldn't have to go to another page to see this, it should calculate and show up in the tagged items page. changing "ac...
James Milroy about 1 year ago in SYNCHRO Perform / Progress Measurement 1 Future Consideration

Composable Filters in Perform

Feature to allow a user to compose their own filters, based on the available fields, in the different Perform screens. As an example, a user in the Work Inspector could create their own filter, based on any/all of the Work Reference attributes, to...
Luke Read over 1 year ago in SYNCHRO Perform / Program/Schedule Collaboration 0 Future Consideration

Option to Link Tagged Items to Revised/Current Qty/Hrs

Hi, would be great to have a tick box where I can select to make the activity's revised/current qty/hours, align automatically to whatever the tagged item list contains. When I import, it assigns to the Tagged item register and items values automa...
David Viola almost 2 years ago in SYNCHRO Perform / Progress Measurement 0 Future Consideration

Allow display of WBS code in the quantity progress page

We frequently handle multiple activities with similar names due to similar nature in the same programme (e.g. submissions and approvals of similar installations). Without WBS code it is difficult to identify which specific work package it is about.
Pak To Hui 12 months ago in SYNCHRO Perform / Progress Measurement 2 Future Consideration

Include filter for start and finish dates in the activity list view

To include actual start and finish date in the filter to view activities under the framework of the WBS.
Pak To Hui 12 months ago in SYNCHRO Perform / Progress Measurement 3 Future Consideration

To include percent complete at the activity list

Would it be possible to use a % complete tag to replace the fixed icon at the shortcut to progress tab?
Pak To Hui 12 months ago in SYNCHRO Perform / Progress Capture 3 Future Consideration

Option to automatically change the activity progress % to 100% when the finish button is pressed.

No description provided
Pak To Hui about 1 year ago in SYNCHRO Perform / Progress Measurement 1 Will not implement

Add support for Notifiable Users to the Bulk Assign page

Bulk Assign currently allows a user to manage Owners, Subcontractors and Clients. This feature would allow Notifiable Users to be managed in the same way
Luke Read about 2 years ago in SYNCHRO Perform / Program/Schedule Collaboration 0 Planned