Include Critical Path Test in the Schedule Health Check

The Schedule Heath Check report mentions the Critical Path Test as item 12. However the report does not perform the check automatically, instead the user should perform the test manually. With this addition the full DCMA-14 test can be performed with just one click.


Also refer to forum topic https://communities.bentley.com/products/construction/f/synchro-construction-forum/225469/schedule-health-check/696079#696079

  • ADMIN RESPONSE
    Jun 6, 2023

    Thank you for submitting this idea. Unfortunately we will not consider it at this time. We will re-consider it when more users request it. Thank you for your feedback and we appreciate it!