Project schedule in Control is not matching 4D Pro. It seem to be showing the planned date in Control, rathe then the Actual date. I checked on another project and seen the same behavior.
This user is obviously expecting to see the same Gantt/schedule as in SYNCHRO 4D Pro which represents the actual dates.
Gantt showing July 26th when the actual start date is April 9th
Hello. I wanted to follow up on this suggestion to see if there has been any consideration for implementing this in a future release?