Able to progressing for Resource Group to Task

Right now, Field only can do progressing if the Resource directly link to Task, progressing is not working if we link resource group to task. In Pro, sometime we need to link resource group to task for better grow simulation. Need to improve Field...
Indrawan Wijaya about 4 years ago in Field / Status update | Resources 1 Planned

Button in email that redirects directly to Synchro Field

When you receive an email, you only have a button that sends you to Synchro Control. We should have the option to redirect to the application directly.
Yessica Andrade Barbosa 12 months ago in Field / Forms | Forms 0 Future Consideration

Ability to read a QR/bar code in forms

Ability to read a QR/bar code in forms and use the infrmation for: populating a textbox/numberbox link to documents/data n SYnchro/alim/PW compare the data to a data linked from ALIM e.g. asset numbers
Kiril Tasev 12 months ago in Field / Forms | Forms 0

[07] Progressing Task

Need to able give progress on task level in the Field App.
Guest over 4 years ago in Field / Status update | Tasks 0 Planned

Collaboration Tracking in Forms

Should be a feature in Forms that allows us to know if another person has a meeting draft open, for example or is opening a form at the same time
Joana Isabel Neves Gomes 7 months ago in Field / Forms | Forms 0

Can Due Date on form be defaulted to TODAY()+X number of days?

By default can the due date be "X" number of days from the date the form was created?
Dan Sheldon over 2 years ago in Field / Forms | Forms 1 Will not implement

The Map Layers doesn't support weather

Would like to be able to see Radar and other map-related weather items as you can see in the Map view in Control. This is needed to attach to forms to show why a delay may have happened
Dan Sheldon over 2 years ago in Field / Forms | Forms 0 Future Consideration

Cross section selection tool on other views

It can be hard to select lines, items or layers in congested areas of the model. Especially when you have big ol construction fingers. It would be very helpful if the Cross-section selection tool was available on all views for easier model selecti...
Thomas Schimpf over 2 years ago in Field / Models | Tools 0 Future Consideration

Pointcloud data on Model in Synchro Field - Currently when adding a Imodel to Synchro, the pointcloud data is visable on the web version but not of synchro field app

Pointcloud data on Model in Synchro Field - Currently when adding a Imodel to Synchro, the pointcloud data is visable on the web version but not of synchro field app
Ann-Marie Baldwin 7 months ago in Field / Models | Display 0

Can progress be performed without 3D

For some projects the Client may not want or may not have a iModel to upload, but have developed a schedule (wbs and tasks). Synchro Field usually allows select the 3D objects and assign progress directly to them (after that tasks are progressed t...