Improving bulk imported 'inspections work scope' transparency within the inspection WBS / Hierarchy
Improving bulk imported 'inspections work scope' transparency within the inspection WBS / Hierarchy - by adding the required inspections to the items / tags. Currently the WBS shows the parent / child / items so work scope; post import is not visi...
Add Contingency Transfer (CT) to contract (similar to Change Order)
CT is a line item in the SOV that is already funded and is used to cover the cost for unforseen conditions. This is not added to the contract or SOV as it is already a line item but the CT would document the use of these funds.
Users want to be able to save profile/cross-section views, with any visible measured dimensions. We should be able to save it to local drive/documents/included in saved views. The use case is to share the information and also attach to Forms. Curr...
When editing the the PDF plan set it would be beneficial to bulk edit items such as Discipline Dates, Type to make initial publishing and QC corrections more efficient
To be able to display annotations in the 3D window accessible from Synchro Control \ Schedule.
For some Use-Cases, it can be necessary to add information to the 4D Model under the form of annotation to highlight specific items (schedule items or Material Resources). It is therefore required to have the possibility to import into Synchro Con...
Thibault Dumas
over 3 years ago
in SYNCHRO Control
1
Future consideration
To be able to visualize in Synchro Control \ Schedule the Predecessors and Successors of a Task and to navigate between them.
As in Synchro 4D Pro to have the possibility when selecting a Task to view in Synchro Control \ Schedule the Predecessor(s) and the Successor(s) of the selected Task. When a task has been selected and its Predecessor(s) & Successor(s) displaye...