SYNCHRO Field

Showing 100

Able to progressing for Resource Group to Task

Right now, Field only can do progressing if the Resource directly link to Task, progressing is not working if we link resource group to task. In Pro, sometime we need to link resource group to task for better grow simulation. Need to improve Field...
Indrawan Wijaya about 3 years ago in SYNCHRO Field / Status update | Resources 1 Planned

Ability to jump between 2D Sheets and 3D Model Views seamlessly

Currently, we can switch from 2D sheets to the previously opened 3D View in SYNCHRO Control, using the following back button - Need something similar for Field as well.
Arpit Prakash about 1 year ago in SYNCHRO Field / Models 1 Future Consideration

Incorporation of an "Undo" feature within the measurement tool

incorporate an "undo" button while you are using any of the civil tools. For example, being able to use the "station/Offset" tool 10 times and only "undoing" the last 3 measurements taken instead of all the 10.
Tony Bonacorsi 10 months ago in SYNCHRO Field / Models | Tools 1 Future Consideration

Enabling measurement tools to convert between different units of measure

have the ability to convert an area measured from Square Feet to Square Yards or Acres automatically with a click of a button like Google Earth's Capability.
Tony Bonacorsi 10 months ago in SYNCHRO Field / Models | Tools 1 Future Consideration

[07] Progressing Task

Need to able give progress on task level in the Field App.
Guest over 3 years ago in SYNCHRO Field / Status update | Tasks 0 Planned

Could additional snap modes be added in Field model tools

Could you add Intersection, Center, and Midpoint Snaps to SYNCHRO Field model viewing?
Dan Sheldon over 1 year ago in SYNCHRO Field / Models | Tools 3 Future Consideration

Can progress be performed without 3D

For some projects the Client may not want or may not have a iModel to upload, but have developed a schedule (wbs and tasks). Synchro Field usually allows select the 3D objects and assign progress directly to them (after that tasks are progressed t...
Derryl Acosta about 3 years ago in SYNCHRO Field / Status update | Tasks 1 Planned

When selecting multiple elements in the model add their quantities together

When selecting multiple elements in the model add there quantities together rather than returning "Varies" If I select two runs of curb and gutter the first being 150ft long and the second being 198ft long I want to get 348ft of curb and gutter in...
Dan Sheldon over 1 year ago in SYNCHRO Field / Models | Display 0 Future Consideration

Resource Status - Update percentage base of quantity

If a task is planned for 10 days to pour 100 cubic meters of concrete. The user would like to be able to update the quantity (cubic meters) using the Field app - Status update
Paolomee Udani almost 3 years ago in SYNCHRO Field / Status update | Resources 0 Planned

Profile Window - Show Multiple Alignments

We often have multiple vertical alignments for a single horizontal alignment. It would be extremely helpful to see all vertical alignments in the profile window. Currently, if we have a roadway profile that is not set active because there are mult...
Ariel Froerer about 1 year ago in SYNCHRO Field / Models | Tools 1 Future Consideration