When managing form with multiple instances it is necessary to be able to filter out some of the statuses and work on the rest. i.e. in attached to filter out the backlog, not suitable and rejected and just leave the live instances. Either by allow...
When using Synchro for a large building construction, we would like to have the possibility to along with the geolocation (X,Y) add the height to represent the different floor of the building. This will be important as some PDF will share the same...
To be able to display annotations in the 3D window accessible from Synchro Control \ Schedule.
For some Use-Cases, it can be necessary to add information to the 4D Model under the form of annotation to highlight specific items (schedule items or Material Resources). It is therefore required to have the possibility to import into Synchro Con...
Thibault Dumas
almost 4 years ago
in SYNCHRO Control
1
Future consideration
Currently, the way this is set up is to remove access for one Role, all other Roles need to be given access, by manually checking on each. If we had a bulk update option, it will be easier to simply remove the restricted users.
Add ability to choose your own fields to sort by in MY WORK
Please add the same ability to pick and choose your own 'view' using the project specific fields that have been filled out in the MY WORK area. ( pic 1 ) Same ability as has been give under the individual forms ( pic 2 ) This will give our contrac...
Functionality for User Fields when using iModel connectors
When a 3D model is imported directly into a Synchro Control project within the Synchro 4D Pro application (using File > Import), it is possible to create user fields. For example, I could import a 3D model and then I could set up a User Field c...
1. Allow Project Admins/Project Owners/Document Controller to Delete Forms created in error in progress 2. Allow admins to download a list of all Bindings. 3. Delete Binding Created by Administrator4. Have a separate Test Area in Control, within t...