Would it be possible to see the human resources allocation by color in the 3d view and be able to see where the human resource overallocation by area and also be able to use this to heat map red orange or green status for high levels of resources
Include Critical Path Test in the Schedule Health Check
The Schedule Heath Check report mentions the Critical Path Test as item 12. However the report does not perform the check automatically, instead the user should perform the test manually. With this addition the full DCMA-14 test can be performed w...
If new elements are added in 3D model for which resources have been created in Synchro 4D pro. There must be option to recreate the existing resources without breaking the links and maintaining the hierarchy as per the 3D model.
At the moment only having a 2D Plot Plan does not lend itself to working on any vertical construction. If we look at the BGR example we will have areas on the plot plan that will have numerous work packs stacked on top of each other and the user w...
Add a tooltip to the disabled "Revise" button in the meatball menus in the Cost grids.
When user doesn't have the "XXX: Create" permission on the associated contract, the "Revise" button will be hidden for Rejected (not already revised) PCOs/COs/PayApps. If a user has the "XXX: Create" permission, but associated contract is unpublis...
Guest
over 2 years ago
in Contracts
0
Future Consideration
Import Non labor data from Primavera P6 to Synchro
Currently I am not able to import non labor data to synchro. If we could import non labor data and apply global changes in the synchro itself it would be beneficial.
Interesting idea on facilitating voice transcription of daily reports. I can see several use cases of this being beneficial especially around safety incidents needing realtime records, issue capturing, or inclement weather. Allowing the inclusion ...
Users: Tony Beamish <tony@mitosisdigitech.com>; Dave Milne <dave@mitosisdigitech.com> Users report that Synchro Field cannot handle their models - we tried set it up for statusing (6.3 and 6.4) without success - see screenshots. We cou...
It's useful for user especially in O&G field which normally deal with pipe or gas line installation. With that Diameter Inch Unit will help a lot to measure the work rate within Synchro.