PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...
PINNED Add enable button to media indexing page to enable service if they have the RBAC role
If I don't have media indexing enabled on my project AND I'm an admin, we need to add a button her to enable it?

All ideas

Showing 99

Incorrect Checkbox location in the Designer

Even though the checkbox are not lining up in the Designer, the output looks correct -
Arpit Prakash over 1 year ago in SYNCHRO Control 0 Planned

Inconsistent padding for Controls in a Section

It seems the padding between Controls is random and there's no way of controlling it - Also, the Control Width should be 100% of the Section instead of the Form. If I set each Control to 50%, they will not stack against each other.
Arpit Prakash over 1 year ago in SYNCHRO Control 0 Planned

Drag windows out of the way in Manage iModel

During the process of managing an iModel there are various windows that come up. Please could you add functionality for dragging these windows to a different position? For example to another computer screen. They are currently static and it would ...
Ruth Fuller over 1 year ago in SYNCHRO Control / Models 0 Planned

Adding Lag values in Task Properties> Links> Predecessors/ Successors do not consistently behave properly

Care must be taken when adding Lag values. This function did not work properly each time. The buttons in the task properties links dialog box were sometimes very touchy and did not function properly. In some cases the correct selection of a button...
Jason Summers almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 4 Planned

Logic tracing when activities are filtered - See attached video for additional details

The inability to filter activities and trace logic where the next activity would show in your visual is a major issue that affects our reporting of critical paths. Those paths can be coded but should be traced rather than simply relying on a code ...
Jason Summers almost 3 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Planned

Allow bulk update for Plansets sheets

With projects having thousands of sheets added as plan sets. Sometimes it is necessary to update some information on multiple sheets after the sheets are published. For a scenario where, for example, the discipline of 100+ sheets needs to be chang...
Hasham Kiani over 1 year ago in SYNCHRO Control / Plan Sets 0 Planned

Gantt Chart with feature to collapse/expand to a certain WBS Level combined with timeline display

At the moment the timeline is only used as a focus time slider feature. Vizualization of the underlying schedule will be very helpful to a understanding of the work ahead. It would be very nice to have the possibility to have the focus time slider...
Brigt Rykkje over 4 years ago in [Archive] SYNCHRO 4D Review 0 Planned

Ability expand multi-line input box within a grid for better visibility

Arpit Prakash over 1 year ago in SYNCHRO Control 1 Planned

Add indicator if form has a missing or corrupt attachment

No description provided
Sarah Albee over 1 year ago in SYNCHRO Control 0 Planned

Wider view upon new form creation

Wider view upon new form creation as the current only covers one third of the screen width.
Kimberly Nazareth Angeles over 1 year ago in SYNCHRO Control / Forms 0 Planned