Pinned ideas

PINNED SYNCHRO Field - Update Task Start date based off Earliest Resource Status
I am not sure if this is planned or not, but when we have the ability to update Resource Status through SYNCHRO Field, there should be an option (or Automatic) to change the status of the Task from Planned to Started, and also update the date to r...

SYNCHRO 4D Pro

Showing 37

Properties generated in ORD are getting dropped in 4D Pro

Properties generated in ORD (item types, etc.) getting dropped in 4D Pro. This has been an issue since Feb 2021.
Matthew Blake almost 2 years ago in SYNCHRO 4D Pro 0 Shipped

Automatching Bug - 'WBS' View vs. 'Custom' View in Task Table

When working with a client today, i found a bug in automatching resources to tasks. The version we are using for the project is SYNCHRO Pro 6.2.3.0 but this may also be occuring in the latest 4D build and should be checked. When executing Resource...
Doug Theret about 2 years ago in SYNCHRO 4D Pro / Auto-Match/Assignments/Resource Usage 1 Shipped

Cost type issue for different resource types

If you add cost to e.g. a resource and you edit the details in the resource properties widget then you get the following options for the type: Also note that the default effective date defaults to 1/2/1970. I think there’s probably no use case atm...
Dimitrios Mitritsios about 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Shipped

All 'Percent Complete Types' property available in task table, no matter the progress type setting

All 'Percent Complete Types' properties available in task table, no matter the progress type setting. For example, if progress type is set to unit, we need to see percent complete for unit, duration, manual & physical as columns in the task ta...
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 3 Shipped

Configuration option to keep new activities visible in filtered view

It is confusing to the user that activities added in a filtered view are not shown/filtered out. An option to keep new activities in a filtered view would help. See attached video
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Shipped

Start and finish dates for predecessors and successors in the links dialog box

When adding logic using the links dialog box, it would be benificial to be able to see the start and finish dates when selecting predecessors and successors. This functionality is available in P6 and is critical for effective scheduling workflows ...
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 1 Shipped

Gap analysis dates jumping bug fix

When performing gap analysis' in SYNCHRO, start and finish dates of activities jump. When we re-scheduled/re-calculated, the correct dates appear and the gap in the schedule is there as it should be based on the schedule logic. However whenever a ...
Jason Summers over 2 years ago in SYNCHRO 4D Pro / Tasks/Scheduling/Gantt Chart 0 Shipped

When multiple user fields are selected allow "copy to text" in CM

Allow user to copy multiple user field names out when needed. Arpit also would be happy to have it.
Stephan Klotz over 2 years ago in SYNCHRO 4D Pro 0 Shipped

Add focus time customization

add py# for project year add pquarter# for project quarter
Shaohua Guan over 2 years ago in SYNCHRO 4D Pro / 3D View/View Properties/Viewpoints/Layouts 1 Shipped

Ability to copy User Field Values from 3D Properties

For iModel workflow, I cannot edit 3D Object properties, but should be able to at least select/copy the values from User Fields- right-click > copy values select value characters by left click > dragging mouse
Arpit Prakash over 2 years ago in SYNCHRO 4D Pro 0 Shipped